Upcoming Projects

Habitat for Humanity Project - the Utility will install 130 feet of 8" SDR21 PVC sewer main at the intersection of Ramsey and Second Avenue which is in Block Ten of the Askew Addition.  It is anticipated that it will take five days of construction beginning Monday February 5th to lay this line.   No roads will be closed for this project.

Upcoming 8th Street Sewer Project - the Utility will be replacing 1760 feet of 8" sewer main and service lines under the street on 8th Street running 200 feet north of NWest Avenue to Newton Street.   This project is scheduled to begin in late February or early March with construction lasting three weeks.  There will be road closures and traffic control on this project.